ContributionsMost RecentMost LikesSolutionsRe: Creating relationshipThanks for the response, Evan! I am a co-worker of Mike's and we are still running into an issue. Our overall issue is that [Project ID] from the project table is not showing up for some records on the Task Resource Assignments Table. I considered using the pass-down method, however the [Task - Project ID] is not linking to the Project record. This is a good back up, but not ideal since the users will need to use extra steps to navigate to the Project record. There is actually already an existing relationship between the Task Resource Assignments table and the Projects table, and some of the Task Resource Assignments are displaying the Project ID through that relationship. A few of them are blank, but still show the correct [Task - Project ID] (hence the graphic showing the indirect relationship). This is where I am getting lost. Why does the relationship only work sometimes? How do we get the unrelated Task Resource Assignments to relate to the Project? Any insight would be greatly appreciated! ------------------------------ Sarah Shimizu ------------------------------ RE: Introducing Pipelines - Webinar Q&ACan we get a list of integrations/apps/channels that are supported with pipelines? ------------------------------ Sarah Shimizu ------------------------------