Can I have a Gantt Chart default to having all groups collapsed?

  • 0
  • 1
  • Question
  • Updated 4 years ago
  • Answered

I have a Gantt Chart for all our tasks related to jobs that are currently active. We would like to have the Gantt Chart just show the timelines for the jobs as a whole, and if we want to look at the individual tasks then we will uncollapse the job. When I go to the Gantt Chart, all of the jobs aren't collapsed and some jobs can have a large amount of tasks and we have quite a few jobs. It can be annoying to have to go through each job and collapse them in order to compare the timelines of the jobs as a whole. Is there a setting I can change that will have the groups default to being collapsed?

Photo of Brandon

Brandon

  • 120 Points 100 badge 2x thumb

Posted 4 years ago

  • 0
  • 1
Photo of Craig

Craig

  • 0 Points
Brandon,

   Currently QuickBase does not have this option for TimeLine reports. Our Uservoice forum is a great place to post enhancement requests that get voted on by other QuickBase users. Thank you.

https://quickbase.uservoice.com/forums/111823-quickbase-product-feedback