Can you assist with a Table Relationship?

  • 0
  • 1
  • Question
  • Updated 4 years ago
  • Answered
Please see attached document for further information.
Photo of Lynne8817

Lynne8817

  • 630 Points 500 badge 2x thumb

Posted 4 years ago

  • 0
  • 1
Photo of QuickBasePros (Laura Thacker)

QuickBasePros (Laura Thacker), Champion

  • 5,466 Points 5k badge 2x thumb
If each Job Schedule record is assigned to just one SubPayroll Table record; then all you need to do is to summarize up to the Job Schedule Table the maximum [Actual Finish Date] from the SubPayroll Table to display the date there.