Hi,The minimum unit of measurement in Gandt Chart is day.We have tasks that are 4-6 hours and these items are displayed as 1 day. Is it possible to change that to hours ?

  • 0
  • 1
  • Question
  • Updated 3 years ago
  • Answered
Photo of Rakesh

Rakesh

  • 0 Points

Posted 3 years ago

  • 0
  • 1
Photo of Ⲇanom the ultimate (Dan Diebolt)

Ⲇanom the ultimate (Dan Diebolt), Champion

  • 29,924 Points 20k badge 2x thumb
That is the problem with these "low code" / "no code" offerings - if there is not a button or configuration in the shrink wrapped interface that you can manipulate you are out of luck. On the other hand it would be simple to use the HighCharts library (which QuickBase uses internally) to generate the custom Gantt Chart from the raw data obtained from the QuickBase API. The data to feed this chart can easily be extracted by the QuickBase API and rendered to a Gantt Chart.