How do I calculate the number of working days between to dates in a business that works 7 days a week . I only seem to be able to do this based on 5 working days . Thanks

  • 0
  • 1
  • Question
  • Updated 4 years ago
  • Answered
Photo of Julie

Julie

  • 0 Points

Posted 4 years ago

  • 0
  • 1
Photo of Ⲇanom the ultimate (Dan Diebolt)

Ⲇanom the ultimate (Dan Diebolt), Champion

  • 30,064 Points 20k badge 2x thumb
ToDays([Date2] - [Date1])