Need formula to include weekday count only

date field [START - HANG] +
numeric field [DW DAYS ALLOWED] =

date field [TARGET SAND DATE]

[START - HANG] = 3/24/2022
[DW DAYS ALLOWED] = 8
[TARGET SAND DATE] should equal 4/4/2022
thank you

------------------------------
BuildPro
------------------------------
This topic has been closed for replies.

MarkShnierYou
Forum|alt.badge.img+24
WeekDayAdd([START - HANG],[DW DAYS ALLOWED])

 you may need to subtract 1 because 1 + 1 = 2, but maybe a 1 day job ends on day 1.


------------------------------