Auto Fill Date Field Based Off of Another Field


Hello, 

I would have three fields that I would like to work together, [Status], [Scheduled Date] and [Completion Date]. Essentially I want the [Completion Date] field to auto fill with the same date as the [Scheduled Date] field once the [Status] field is equal to "Complete". 

Any thoughts on how to make this work? I'm a little new at QuickBase. 

Thanks!
This topic has been closed for replies.

  • Registered
  • March 15, 2017
You will need to set a "dynamic form rule" to populate that date, when your status field is changed.  

If you are an Admin on the account and you open up one of the records
>
In the top right you will see "Customize This Form"
>
After opening up those settings, click on the "Dynamic Form Rules" tab
>
Create a new rule with the needed logic
>
Something to the affect of:

Condition
If [Status] is equal to "Complete"

Action:
Change [Completion Date] to the value in the field [Scheduled Date]

Andreonna,

Are you certain the two dates will always match? Is it not possible that [Completion Date] may occur sooner than or later than [Scheduled Date] ?