I am trying to figure out a formula for duration. my problem is that one set of date is Date/Time, while the other is only Date.

QC Date - Date/Time
Start Date - Date

The QC Date pulls from a relationship, so I don't think I can simply change the QC Date to "date" only because of the relationship.

However, what I am trying to do is determine only the number of days between the two and exclude the "time" portion, if possible.

I thought i was close with this formula, but it does not like the subtraction.

DAYOFYEAR(TODATE([QC DATE CREATED]))-[DESIGN START DATE])

All i need it to do is pull the date and ignore the time stamp - QC date 11/22 - start date 11/20 = 2 days. Is this possible? I looked at other formula functions as well, but to no luck so far.
Thanks!



------------------------------
Bret Osborne
------------------------------
This topic has been closed for replies.

MarkShnierYou
Forum|alt.badge.img+24
This will  give you a Duration result

ToDate([QC DATE CREATED])-[DESIGN START DATE])

Personally I find duration fields confusing to work with.  I prefer to have a  numeric field representing the # of days when dealing with short term time ranges.

This would be a numeric fieldโ€‹

ToDays(ToDate([QC DATE CREATED])-[DESIGN START DATE]))


------------------------------