Hi all, I'm trying to build a project management app but can't do it.
It's pretty simple, there are 3 Workstreams. Under each workstream 3 initiatives. Under each initiative 3 activities.
Each activity has start date and end date.
Thus i would like that every initiative picks on the minimum start date, and the maximum end date of its relevant activities, in order to create a classic Gantt in the end. And that everything would be linked.
Same way, the start and end dates of initiatives would go up to workstreams.

I have created 1 table for workstreams. 1 table for initiatives. 1 table for activities.

Do you know how i could do that?

Also after that i would like to to the same thing for % completion : the progress of each activity would go up the same way and ultimately impact the workstreams automatically.

Thank you in advance for your time

------------------------------
Adil Bennani
------------------------------
This topic has been closed for replies.

AdamKeever1
Forum|alt.badge.img+2
  • Qrew Commander
  • Oct 22, 2019 7:47 PM UTC
Hello Adil,

You have your case well defined. That made it very easy to construct the tables and relationships necessary to fulfill your requirements.

Here is the end result:
=================================================================================================

I started by creating three excel sheets; one for workstreams, one for initiatives, and one for activities. Here is what the data in each sheet looks like:

Workstreams
Workstream1
Workstream2
Workstream3

ID Initiative
1 Initiative1
1 Initiative2
1 Initiative3
2 Initiative1
2 Initiative2
2 Initiative3
3 Initiative1
3 Initiative2
3 Initiative3

ID Activities Start Date End Date
1 Activity1 1/5/2020 2/14/2020
1 Activity2 12/20/2019 1/18/2020
1 Activity3 1/16/2020 3/20/2020
2 Activity1 12/17/2019 1/6/2020
2 Activity2 11/29/2019 2/25/2020
2 Activity3 1/2/2020 2/2/2020
3 Activity1 12/31/2019 2/13/2020
3 Activity2 11/4/2019 12/9/2019
3 Activity3 12/7/2019 2/10/2020
4 Activity1 1/2/2020 2/22/2020
4 Activity2 11/8/2019 11/24/2019
4 Activity3 12/17/2019 2/20/2020
5 Activity1 11/6/2019 1/7/2020
5 Activity2 12/11/2019 2/4/2020
5 Activity3 1/12/2020 3/4/2020
6 Activity1 1/10/2020 3/19/2020
6 Activity2 10/22/2019 11/7/2019
6 Activity3 11/30/2019 12/16/2019
7 Activity1 1/11/2020 3/16/2020
7 Activity2 11/13/2019 1/2/2020
7 Activity3 11/26/2019 2/23/2020
8 Activity1 11/22/2019 12/27/2019
8 Activity2 11/23/2019 1/11/2020
8 Activity3 11/21/2019 2/8/2020
9 Activity1 12/29/2019 2/10/2020
9 Activity2 1/17/2020 3/30/2020
9 Activity3 11/12/2019 11/30/2019

Create each table in Quick Base and then import the data into each table (Record ID#'s will be assigned based on the order of the records and that is where the ID columns in the sheets come in to play for adding relationships later):

Be sure this checkbox is checked:

And each filed should be set to "Create New Field": 

Add a checkbox field for identifying complete activities and a formula numeric field to count complete activities in the activities table:
Use this formula in the [Count] field:
If(
[Complete]=true, 1, 0)​

Create the first relationship:
One initiative to many activities; add summary fields for max end date, min end date, # of activities and total count completed:
Be sure to select ID as the reference field:


Create a formula numeric field in initiatives table to calculate the percent complete:

Create the second relationship:
One workstream to many initiatives; add summary fields for max max end date, min min end date, # of activities and total total count completed:
Be sure to select ID as the reference field:

Create a formula numeric field in the workstreams table to calculate the percent complete:

There you have it.

------------------------------
Adam Keever
------------------------------