When a parent record is added, and a specific "issue type" is selected from the drop down list is there a way to require a task record to be created. The add task is a linked table within the parent record. 

Forum|alt.badge.img+15
  • Quickbase Alumni
  • September 22, 2026

Add one more table to the design.

Parents Table,  lets call it Customer Complaints

Issue Table

Issue Tasks Table

Customer Complaint Tasks 

When you set the Issue for a particular Customer Complaint, fire a pipeline that will search for the Issue Task for that Issue.

The create a Complaint Task record for Issue Task

 

 

So if your Issue was something like "Customer wants a refund"   The Issue Tasks might be 

Send RMA

Inspect Return

Credit Customer Credit Card

 

All three tasks are now child records of the Customer Complaint record.