Question

AUTOMATIONS

  • October 8, 2018
  • 0 replies
  • 15 views

I am trying to get rid of our template and Import All Tasks button on the project.
Was excited to try the newer Automations function however it is not working as expected.

When a new project is created, i need to add the first task "RFQ Document Upload". 

Ideally, i would like to be able to do the following

1. when a project is added, add RFQ Document upload task to the task table.
2. When RFQ Document upload task is complete, add BOM COSTING task to the task table.
3. When BOM Costing task is complete, add BOM REVIEW/TOOLING/LABOR task to the task table.
4. When that task is complete, add SALES Review & Quote task. 

I am starting safe and only setting up the first action [add first task when project is added]. This is not working. I add a new project and the tasks table is still empty after saving. 




This topic has been closed for replies.

  • Author
  • Quickbase Alumni
  • October 8, 2018
OKAY, so i have realized the automations are creating the first task, however it is not showing up on the "related tasks" table on the project. solution?

Did you remember to populate the field [Related Project] with the Record ID of the project record?

  • Author
  • Quickbase Alumni
  • October 8, 2018
Where and when do i populate the field [related project]? I thought the point of the automations is to automatically create a task based on the new project created. 

Related field is not an option as a field i can choose on my automation setup. Even thought it IS a field used in my tasks if i setup manually.

Automations are smart but then dint read your mind.

You need to add a field to be populated when you are creating the Task. That field is typically called Related Project and the Automation will allow you to click on the �lines� to the right side of that field and select which fields from Projects to populate it with. So choose Record ID.