I would like to amend the following formula so that the end result is always adjusted to be a following Friday date. Will appreciate some help. 

 If([Category] = "PNP", WeekdayAdd([Equip Reqd By],-21), 
WeekdayAdd([Equip Reqd By],-14))
This topic has been closed for replies.

Try this

var date RawDate = If([Category] = "PNP", WeekdayAdd([Equip Reqd By],-21), 
WeekdayAdd([Equip Reqd By],-14));

LastDayOfPeriod($RawDate, Weeks(1),Date(2017,5,20))

What does is to take the Period starting on a Saturday (it does not matter which Saturday) and based on a period length of 1 week, it calculates the Last Day of the Period, which of course must be a Friday if the 1 week period starts on a Saturday.

  • Author
  • Quickbase Alumni
  • May 18, 2017
This is a great solution.  Works.  I noticed  that you have used certain date (2017,5.20).  Will that need to be amended at any stage? 

That field will only needs to be changed if the world goes to a 6 or 8 day week as the new Global standard.  That seems unlikely any time soon!  So no, it can be any Saturday even one 200 years ago or in the future.

  • Author
  • Quickbase Alumni
  • May 18, 2017
Haha  cheers