Formula to calculate a future date


I must say...  Date field typically don't give me a hard time; however, this one has me stumped...

I have a [Period of Performance Start Date], a [Contract Duration] field (numeric field) and a [Period of Performance End Date] (formula Date).  

My example is:
[Period of Performance Start Date] 02/08/2019
[Contract Duration] 5.5 (meaning 5 1/2 years)
[Period of Performance End Date] - 08/07/2024 -
Sample Formula below:
AdjustYear([Period of Performance Start Date], [Contract Duration])

BUT IT ISN'T WORKING.  I assume it is because I have a decimal in my [Contract Duration] field, but I don't see any other way to swing this.  Please Help!


------------------------------
Amber Polston
------------------------------
This topic has been closed for replies.

MarkShnierYou
Forum|alt.badge.img+24
If you allow the contractor ration to be entered in decimal years then you were obviously not super concerned about the accuracy of the exact number of days.
So try this

[Period of Performance Start Date] + Days(Round([Contract Duration]*365.25))


------------------------------
Mark Shnier (YQC)
Quick Base Solution Provider
Your Quick Base Coach
http://QuickBaseCoach.com