Question

How can I calculate the duration of a project to display in a table? I have a field ""Date Created"".

  • May 9, 2017
  • 0 replies
  • 54 views

How can I calculate the duration of a project to display in a table? I have a field ""Date Created"".
This topic has been closed for replies.

  • Author
  • Quickbase Alumni
  • May 9, 2017
Not only do I need to see from "Date Created" to "Date Completed", but would also like to see "Date Created" to Todays Date if not completed.

Try this as a formula numeric field called [Project Duration Days]

var date EndDate = IF(not IsNull([Date Completed]),[Date Completed],Today());

ToDays($EndDate - ToDate([Date Created]))

The built in field for [Date Created] is actually a date/time field type so that is why it needs to be converted to a date with the ToDate function.

  • Author
  • Quickbase Alumni
  • May 10, 2017
Worked Perfectly!!!   Thank you so much!!