Is this weakness with tasks?

  • August 8, 2017
  • 0 replies
  • 17 views

I have a tasks table which has sequential dependency.  So the first task is what is driving others as being predecessor.  I can mark my tasks as complete with a finish date but not quite  the first one as it comes with the following error.  Am I not supposed to modify this and if I cannot how do I ensure that I hide this from users' view? 


  
This topic has been closed for replies.

  • Quickbase Alumni
  • August 11, 2017
It looks from your screen shot like you are trying to make this task a predecessor of itself, thereby creating a circular reference. The first task of a project shouldn't have any predecessors. At least that's the way we do it in our project-task app.

  • Author
  • Quickbase Alumni
  • August 12, 2017
Thanks for the feedback. No it has successors. And siomeone was trying to change the date whioch is coming from the parent project table.  May be I should ake it read only.