Subtract Weekdays from Date to get start date

  • August 4, 2017
  • 0 replies
  • 53 views

So this is what I have. [Desired In-Market]-ToDays,[Est Days]

I am wanting to get a start date for a project.
Team Members can enter the date, pick a schedule and this calculation should spit out when a project should start. The [Est Days] is the number of working days/weekdays that the project should take. Sooooo how do I do this?
This topic has been closed for replies.

Is this not a thing? Anyone, anyone, Bueller?

  • Registered
  • August 8, 2017
Your field [Desired In-Market] is date/time, your field [Est Days] is numeric, the field [Start Date] is formula - date/time:

WeekdayAdd (
ToDate([Desired In-Market]),([Est Days] * -1)
)