what is meaning of Predecessor

  • May 8, 2014
  • 0 replies
  • 77 views

While creating new field in table. I saw Predecessor option. Please tell about this


This topic has been closed for replies.

They ate used to manage due date on tasks where the tasks are sequential and have dependencies.

QuickBase has thematic features of Microsoft Projrct.

Example to build a house:
Dig hole
Lay foundation
Build walls
Build roof

Each task can have a dependency that it can't start until one orote previous tasks have been completed.

Forum|alt.badge.img+1
How can I use this field as I am in need of what you explained this field can do. 

True Example: 
I want things do get done in an order and one should not be done until the one before has been completed.

How do I implement this or program this field?  Formula?