Forum Discussion
AswinBabu
5 years agoQrew Member
Thank you for replying. I will check this out
------------------------------
Aswin Babu
------------------------------
------------------------------
Aswin Babu
------------------------------
MarkShnier__You
Qrew Legend
4 years agoAn automation concurrently support 50 steps but I would suggest limiting yourself to 25. You can have those first 24 steps create 24 children and populate a field with child number in each step from 1 to 24.
You can then look up the number of children that were required from, the parent down to the children and have Step 25 delete any excess children where their child # was higher than what was required.​
------------------------------
Mark Shnier (YQC)
Quick Base Solution Provider
Your Quick Base Coach
http://QuickBaseCoach.com
mark.shnier@gmail.com
------------------------------
You can then look up the number of children that were required from, the parent down to the children and have Step 25 delete any excess children where their child # was higher than what was required.​
------------------------------
Mark Shnier (YQC)
Quick Base Solution Provider
Your Quick Base Coach
http://QuickBaseCoach.com
mark.shnier@gmail.com
------------------------------
Related Content
- 3 months ago