Any success in achieving this? I saw that for new Gantt Plugin they mange to achieve it and User can specify Holidays days in dedicated table, and Gantt is skipping those days as not working.
I wonder if this is Plugin functionality, or they manage to do it via Native Quickbase formulas?
I am having similar problem to solve to calculate End date of my task based on duration & start Date. But I want to include additional Custom Holidays to this. Additional Challenge is that I need to have different holidays per country, which makes it even more complex😀.
------------------------------
Adam Krzyzanek
------------------------------
This community post here outlines a somewhat brute force method to calculate the number of holidays in a date span.
There are now more elegant methods using Formula Queries. I will see if I can find an example. .
------------------------------
Mark Shnier (Your Quickbase Coach)