Forum Discussion

AdamKrzyzanek's avatar
AdamKrzyzanek
Qrew Captain
2 years ago

Gantt Chart - calculation task end Date/Time

Question: If there a ways to calculate Project Management tasks with "duration" less than 1 day?

Background:
I am managing Initiatives delivery in my application and my users asked if we can calculate "Projected End Date" of task with task duration smaller than 1 day.

Let say I have tasks which takes 0.1 day (2.4h ) or 0.2 (4.8h) I would like to calculate it as less than 1 day.

Example: If 3 tasks below 1 day are after each other it should show as Starting and Ending at the same day.

What I currently have:
1) [Starting Date] - Work Date
2) [Projected End Date] - Work Date (where:


3) [Duration] - Numeric
4) [Pred] - Predecessor

I tried to add [Real Duration] = Duration field but it cannot be used for "Time span field"



------------------------------
Adam Krzyzanek
------------------------------
  • Does anybody have any idea how to achieve it?



    ------------------------------
    Adam Krzyzanek
    ------------------------------
    • AdamKrzyzanek's avatar
      AdamKrzyzanek
      Qrew Captain

      Kind reminder :)



      ------------------------------
      Adam Krzyzanek
      ------------------------------