Forum Discussion
QuickBaseCoachD
7 years agoQrew Captain
Can you post your formula and the complete error message?
PriscillaFramar
7 years agoQrew Trainee
Used what you suggested except Date Delivered is Actual Finish Date.
If(
[Status] = "Delivered"
and [Actual Finish Date] >= ToDate([Calculated Finish Date]),
ToDays([Actual Finish Date] - ToDate([Calculated Finish Date])),
Max(0, ToDays(Today() - ToDate([Calculated Finish Date]))))
The line: ToDays([Actual Finish Date] - ToDate([Calculated Finish Date])), give me the warning of �Expecting Duration but found number�