ArchiveUserQrew Captain8 years agohow to calculate overdue workdayshow to calculate overdue workdays? Currently, I use the formula below to get overdue days of my tasks. It works well. However, I'd like to make the overdue day is workday instead of calendar day....Show More
AudraMicklesQrew Trainee7 years agoTry:WeekdaySub(Today(),[Projected Finish], ToDays(Today() - [Projected Finish])