2 years agoQrew Member
More Formula Fun
In my Project Manager APP, I have a User Field Associated with Projects. I want to calculate the time In between when every User Previous Project ends to When their New Project Starts.
So the New Project Start Date - the previous Project end date when assign to the same Person. Record 2 (assigned to this person) Project Start Date - Record 1 (assigned to this same person) Project End Date.
------------------------------