Re: Timeline Report / Calendar Report

Unfortunately, not the way that you have it structured. The Timeline Report (Gantt) utilizes individual records with a Start and End date.

------------------------------
Blake Harrison
bharrison@datablender.io
DataBlender - Quick Base Solution Provider
Atlanta GA
404.800.1702 / http://datablender.io/
------------------------------

8 Replies

  • AlexBennett3's avatar
    AlexBennett3
    Qrew Trainee
    So I would have to break up my Job record with all the data into multiple to be able to show all of them up on a Timeline Report?

    ------------------------------
    Alex Bennett
    ------------------------------
    • BlakeHarrison's avatar
      BlakeHarrison
      Qrew Captain
      If you want to show the Start / End time for each Department on a Timeline report, each Department would have to have be a child record to the Job and your report would be done on that child table.

      ------------------------------
      Blake Harrison
      bharrison@datablender.io
      DataBlender - Quick Base Solution Provider
      Atlanta GA
      404.800.1702 / http://datablender.io/
      ------------------------------
      • AlexBennett3's avatar
        AlexBennett3
        Qrew Trainee

        So this is the layout of my app, there are 7 departments that I'm trying to display on a calendar or timeline to visually display their durations in 4 phases. Right now this Schedules table is a child of my Jobs table. So you're saying I'll have to Split each department into separate records? If so, how would I display all the records needed separately on a Timeline Report?


        ------------------------------