Change successor activity status automatically based on predecessor status.

I have projects made up of activities. Some activities have predecessors. I need to have the successor status change from ?Waiting? to ?Not Started? when the predecessor status changes to ?Complete?.

How do I get this to happen automatically?
  • I have this issue too.  Was hoping to accomplish via a Webhook.  Were you able to find a solution?