EvanMartinez
5 years agoModerator
Hi Christine,
Unfortunately that part of the ask does complicate things, the report link suggested only gives you visibility and accessibility to the fields and records you have in your table. Since you would want to track their status at a specific date you would need a place to hold the data of the status as of that date, most likely in an audit or historical status table related to the Project Tasks table.
The tables job would be to store records of the history of the status of a Project Task, every time it is updated a new record would be created to say it went up from for example 10% to 20% on April 20th and was edited by John Smith, then the next time it is edited from 20% to 30% on April 22nd another record would be created to track that history. This can either be done manually by a user every time they edit the status or it can be done by a Pipeline so that every time the percent complete of a project is changed it is automatically logged and stored in the historical table with the relevant data so a user never has to worry about it but you as an admin can report off and see it all.
The advantage there is you can capture that data and be able to report on and summarize it all just like you can any table of data in Quickbase, it just requires a relationship between Project Tasks as the parent and your Project Tasks Status Historical table to help you keep all that data organized and stored. Otherwise you would just be writing it into a bunch of fields in your Progress Notes table that would be much more complicated to report on. I know it is a more complex workflow but I hope the suggestion is helpful.
------------------------------
Evan Martinez
Community Marketing Manager
Quickbase
------------------------------
Unfortunately that part of the ask does complicate things, the report link suggested only gives you visibility and accessibility to the fields and records you have in your table. Since you would want to track their status at a specific date you would need a place to hold the data of the status as of that date, most likely in an audit or historical status table related to the Project Tasks table.
The tables job would be to store records of the history of the status of a Project Task, every time it is updated a new record would be created to say it went up from for example 10% to 20% on April 20th and was edited by John Smith, then the next time it is edited from 20% to 30% on April 22nd another record would be created to track that history. This can either be done manually by a user every time they edit the status or it can be done by a Pipeline so that every time the percent complete of a project is changed it is automatically logged and stored in the historical table with the relevant data so a user never has to worry about it but you as an admin can report off and see it all.
The advantage there is you can capture that data and be able to report on and summarize it all just like you can any table of data in Quickbase, it just requires a relationship between Project Tasks as the parent and your Project Tasks Status Historical table to help you keep all that data organized and stored. Otherwise you would just be writing it into a bunch of fields in your Progress Notes table that would be much more complicated to report on. I know it is a more complex workflow but I hope the suggestion is helpful.
------------------------------
Evan Martinez
Community Marketing Manager
Quickbase
------------------------------
- ChristineWhite5 years agoQrew Assistant CaptainThank you for the suggestion. I may try creating the Task table in the Progress Notes table and updating the Project using pipelines.
------------------------------
Christine White
------------------------------- ChristineWhite5 years agoQrew Assistant CaptainI am also going to give your suggestion a try and see which the team prefers. Thanks so much
------------------------------
Christine White
------------------------------- ChristineWhite5 years agoQrew Assistant CaptainI am trying this now. Wondering if there is a way to relate records to the Progress Notes by editing the Project Report link details in the pipeline?
------------------------------
Christine White
------------------------------