6 years agoQrew Member
Any advice from someone on this?
------------------------------
Justin Finkelstein
------------------------------
------------------------------
Justin Finkelstein
------------------------------
- MarkShnier__You6 years agoQrew Legend I could probably help you , but I don't have any pre-built formula that I can post. We would need to work one on one on a consulting basis.
 ------------------------------
 Mark Shnier (YQC)
 Quick Base Solution Provider
 Your Quick Base Coach
 http://QuickBaseCoach.com
 mark.shnier@gmail.com
 ------------------------------- JustinFinkelste6 years agoQrew MemberJust looking for someone to point me in the right direction. Any help would be amazing!
 ------------------------------
 Justin Finkelstein
 ------------------------------- NeilSchneider6 years agoQrew CadetIt's been a while - but what you can do is:
 Count the number of days between the start and end dates ToDays(startdate - enddate)
 Divide that number by 7.
 Multiply by 4 to get the work days in whole weeks
 Then you need to adjust for the number of days that remain that are work days for example;
 if there are 10 days in the period, and the first day of the period is Monday.
 Mo Tu We Th Fr Sa Su Mo Tu We
 Then you have 4 work days + Mo Tu We all of which are work days
 So 7 total work days
 Basically the adjustment is calculated as follows:
 If the first date Mon
 - If the number of remaining days is less than 7, add 3
 - If the number of remaining days is less than 3, and all of them
 ...
 That's the basic formula.
 ------------------------------