MarkShnier__You
2 years agoQrew Legend
I have not tested this, but when you configure a Predecessor field you set the field which represents the start date and the end date. Try making a new field of type Formula WorkDate which adds extra days to your existing Finish date, with a formula of WorkDateAdd([End Date],2)
then use that new field in the setting fir the Predecessor field
------------------------------
Mark Shnier (Your Quickbase Coach)