Forum Discussion

Re: Can I create a Gantt chart for milestones (start and end dates) within a single record?

Hello,
Is there an answer on this one. I thought I read somewhere that you cant create a Gantt chart using dates that are housed inside 1 record. If thats the case, is there a way around this? Maybe create another table for those dates?

------------------------------
Megan Hardison
------------------------------

1 Reply

  • BlakeHarrison's avatar
    BlakeHarrison
    Qrew Captain
    That is correct. You cannot create a Gantt chart on a single record - this has to be done with a Parent/Child table structure where each Milestone is represented by a single Child record. For example, the Project would be a Parent and it would have multiple Tasks (child). Each Task could be labeled as a Milestone.

    ------------------------------
    Blake Harrison - DataBlender.io
    Quick Base Solution Provider
    ------------------------------