CarolynHendryc1
6 years agoQrew Member
Schedule hours over multiple weeks in one entry
We have a Project Tasks table where each task has a Start Date, Duration, Budget Hours, and Employee assigned to it. One of the most important pieces of data we need is how many hours each employee is scheduled per week.
The problem comes when we have a task that will happen over multiple weeks. The hours for the employee will only show up the first week, but I need them spread out over all the weeks.
For example, I have a task with a start date of June 3, duration of 50 days, and 60 budget hours. On the summary table it shows that employee as having 60 hours booked the week of June 3 and 0 hours over the following weeks. I'm stuck as to how to write a formula to split out these hours over the multiple weeks.
We have thousands of tasks and I don't want our scheduler to have to enter multiple entries per task to break things out into weeks.