It sounds like you were saying that there are task dependencies, And that task 2 cannot start until task 1 is completed. That would involve use Predecessors.
https://help.quickbase.com/user-assistance/about_dependencies.html In practice these are somewhat of a pain to set up unless you have a standard set of tasks which you can copy into a new project which already has the dependencies established. Then the copy master detail function does a magnificent job of this. The whole concept of predecessors is a skill area to be acquired. You might want some one on one assistance after reading up on it.
------------------------------
Mark Shnier (YQC)