- LauraThackerQrew CaptainCheck your "Predecessor" field is properly setup and actually references a Start Date and a Duration
- EricaSimmonsQrew TraineeAnd the Start Date is a Work Date
- EricaSimmonsQrew TraineeYes, it does reference a start date, and a duration.
- LauraThackerQrew CaptainI would probably need to see it - can you contact me offline so we can try to resolve?
- ArchiveUserQrew CaptainWhat was the resolution to this? I am having the same issue.
- EricaSimmonsQrew TraineeI had to get Quickbase Support involved. They're currently working on a resolution, but have not fixed it yet.
- MMQrew Memberalso, make sure you're tasks are linked to "Work Dates" and not just a regular date field.
- ArchiveUserQrew CaptainGreat - thanks Erica. That's what I suspected based on some other threads I've seen. I hope they get this worked out, it's pretty critical for scheduling.
- EricaSimmonsQrew TraineeThanks for weighing in. They are Work Dates. Quickbase has still not provided a solution.
- EricaSimmonsQrew Traineefor anyone following this thread - the predecessors field was corrupted. I don't know if it was on our application alone, or all applications up to a certain point. I had to delete the field, and create it again.