Discussions

 View Only

Yes, You can use pipeline to figure predecessors - See How

  • 1.  Yes, You can use pipeline to figure predecessors - See How

    Posted 05-16-2022 21:29

    I've spent better part of last 1 hour to figure, so posting this for others. Thank you @Mark Shnier @Quick Base Junkie@ @Quick Base Junkie for posting numerous examples before me.

    I've a table containing my template task with sequence in order below
    TaskName | Task Sequence
    Task A | 1
    Task B | 2
    Task C | 3
    Task D | 4
    Task E | 5

    Challenge : When I copy these template task to Project task , I want predecessors to be define automatically via pipelines

    Solution
    After you've created a pipeline to copy template task to project task table , use update record to define predecessor field (AboveTask) here to

    {% if c.task_sequence|int >1 %} {{c.id|int-1}} {% endif %}



    ​​​

    ------------------------------
    Prashant Maheshwari
    ------------------------------