Forum Discussion
ArchiveUser
8 years agoQrew Captain
I believe you should be able to add 2 other fields - 'Offset' and 'Successor Start Date' - to adjust the Start Date of the Successor on a per-task basis. Essentially, your Predecessor field would look at the 'Successor Start Date' instead of the 'End Date' field. "Successor Start Date' would be a formula field that added the number of days in 'Offset' to the original 'End Date'.