Project management issue - Gantt
Hi all, I'm trying to build a project management app but can't do it.
It's pretty simple, there are 3 Workstreams. Under each workstream 3 initiatives. Under each initiative 3 activities.
Each activity has start date and end date.
Thus i would like that every initiative picks on the minimum start date, and the maximum end date of its relevant activities, in order to create a classic Gantt in the end. And that everything would be linked.
Same way, the start and end dates of initiatives would go up to workstreams.
I have created 1 table for workstreams. 1 table for initiatives. 1 table for activities.
Do you know how i could do that?
Also after that i would like to to the same thing for % completion : the progress of each activity would go up the same way and ultimately impact the workstreams automatically.
Thank you in advance for your time
------------------------------
Adil Bennani
------------------------------
It's pretty simple, there are 3 Workstreams. Under each workstream 3 initiatives. Under each initiative 3 activities.
Each activity has start date and end date.
Thus i would like that every initiative picks on the minimum start date, and the maximum end date of its relevant activities, in order to create a classic Gantt in the end. And that everything would be linked.
Same way, the start and end dates of initiatives would go up to workstreams.
I have created 1 table for workstreams. 1 table for initiatives. 1 table for activities.
Do you know how i could do that?
Also after that i would like to to the same thing for % completion : the progress of each activity would go up the same way and ultimately impact the workstreams automatically.
Thank you in advance for your time
------------------------------