Progressive Start Date In A Time Line Chart

  • 0
  • 1
  • Question
  • Updated 1 year ago
  • In Progress
In a a time line chart start and finish dates are hard coded.   If we have already delivered projects in the past and we only want to focus on what is coming up and show months/weeks ahead only, the start date has to be amended each time.  Wondering if there was a way to have a dynamic start date so that it moves with the year progressing to avoid seeing  blank columns for previous periods.  Not too sure if there is an option. 
Photo of Arshad Khwaja

Arshad Khwaja

  • 3,132 Points 3k badge 2x thumb

Posted 1 year ago

  • 0
  • 1
Photo of Matthew Neil

Matthew Neil

  • 31,438 Points 20k badge 2x thumb
Have the start date for the report or the "Progressive" start date be:  Today()

Then your report will be a little more dynamic.
Photo of Dinesh

Dinesh

  • 202 Points 100 badge 2x thumb
Another way could be to link records by using Predecessor field so that you can have a more meaningful derived date field from a previous record which is already completed or in progress....the way you will do it for a project schedule and produce a gantt chart!
Photo of Arshad Khwaja

Arshad Khwaja

  • 3,132 Points 3k badge 2x thumb
Thanks Matt.  Unless I am not understanding,the 'starting date' in a timeline report is linked to a calendar and cannot be amended.